19. Fabrication (Off Site) and Erection of 3 Nos. Lube Oil Cooler Support Frames for the RVSG-Owned, 3 No. 10 MW Gas Turbine Plant at Trans-Amadi, Port Harcourt : NEGRIS, Main contractor [2001]. 20. Constructions and Installation of a Trip Tank on Bintang Kalimantan Oil Drilling Rig: FORASOL [2001]. 21. Technical Auditing of a Broken - Down Sewage Treatment Plant at the Port Harcourt Area Office: PPMC [2001]. 22. Piping (Stainless Steel and Carbon Steel) of RVSG-Owned, 3 Nos. 10 MW Gas Turbine Plant at Trans-Amadi: NEGRIS , Main Contractor [2002]. 23. Fabrication [Tank Support, Plant Basement and Installation Structural Frames], Piping and Installation of Potable Water Treatment Plant at the SPDC Facility, Bonny: NEGRIS , Main Contractor [2002].
|